Technical Guidance Notes

12.5 - Construction joints

With composite floor slabs, it is possible to achieve continuous concrete pours in excess of 1,000m2.

Where construction joints are required, these should always be formed as close as possible to the deck support at the butt joint in the deck sheets. The distance from the centre of the end support to the stop end should never exceed one-third of the span between the supports (Refer to Fig 12.5a).

Click here for high-res version of Fig 12.5a - Construction Joint

Refer Concrete Society TR75 Section 7.5 & SCI P300

Construction joints should be formed using either timber or one of the proprietary joint systems available for use on composite floor deck profiles. Where a day joint is required, adequate continuity reinforcement must be provided either by extending a sheet of mesh or additional bars through the joint location to provide slab continuity between pours.

SMD Logo
InstagramXLinkedInFacebookYouTube

Structural Metal Decks Limited

The Outlook, Ling Road, Poole, BH12 4PY

Registered in England & Wales No. 03560591

Tel: +44 (0) 1202 718898

SMD® 2025