
In some instances concrete encased perimeter beams may be specified as part of the fire design. It is recommended that the beam is encased to the top flange level off-site, therefore enabling the decking to be installed to the beam top flange as normal.
Where it is not possible to carry out the concrete encasement off-site, the following procedure is possible using R51+ profile:

Click here for high-res version of Fig 7.3a
A similar process to that detailed above can be followed where a building or basement has perimeter concrete walls with continuity reinforcement extending into the floor slab, providing the formwork is designed to support the weight of the decking, wet concrete and construction imposed loads to avoid the need for adjacent temporary propping.