Developed in partnership with ArcelorMittal Sheffield Ltd, TAB-Deck™ fibre reinforced concrete should be installed, cured and finished in exactly the same way as non-fibre reinforced concrete. The only fibre that has been extensively tested for use in TAB-Deck™ projects is Arcelor Mittal Sheffield Ltd's HE 1/50 steel fibre (refer to Fig 13.6a) at a dosage of 30kg/m³.

HE 1/50 Technical Specification:
Tensile strength of drawn wire;
Concrete Design
The specific mix design will always depend on the local materials available but should follow these basic guidelines:
Mixing
The best method for integrating the HE 1/50 steel fibre into the fresh concrete is by blast machines, available on request from ArcelorMittal Wire Solutions. This is a self-sufficient operation where the steel fibres are blown into the preloaded ready mix truck allowing easy homogenisation of the steel fibres into the concrete mix.
Alternatively, the steel fibres may be loaded via mobile conveyor belts or placed on the aggregate belt at the ready mix plant.
Finishing
Where a power float finish is specified when using steel fibres, consideration should be given by the Project Team for an application of a fibre suppressant dry shake topping which would significantly reduce the likelihood of exposed/protruding fibres becoming apparent in the final surface finish.
For further information and design guidance contact ArcelorMittal Sheffield Ltd or head to our website.