Care should be taken when utilising the decking as a working platform, or storing materials for following trades, as any damage resulting from these activities will require a site inspection with any damaged sheets likely to require replacement. 
  
 
+
'''Important:''' For areas exhibiting damage, the concrete pour must not progress until an appropriate inspection has been carried out and any remedial action implemented.
 
+
Body - First line  
+
 
+
Body - Last line
+
  
  
Line 11: Line 7:
  
  
Other items within 12.0 - Concrete:-
+
Go to '''[[12.5 - Construction joints|NEXT]]''' section
: [[12.1 - Site considerations]]
+
: [[12.2 - Temporary propping]]
+
: [[12.3 - Cleaning the decking]]
+
: [[12.4 - Damaged decking]]
+
: [[12.5 - Construction joints]]
+
: [[12.6 - Reinforcement drawings and bending schedules]]
+
: [[12.7 - Concrete mix requirements]]
+
: [[12.8 - Placement]]
+
: [[12.9 - Surface finish]]
+
: [[12.10 - Surface flatness]]
+
: [[12.11 - Curing]]
+
: [[12.12 - Post-installation characteristics]]
+

Latest revision as of 09:58, 21 March 2017

Care should be taken when utilising the decking as a working platform, or storing materials for following trades, as any damage resulting from these activities will require a site inspection with any damaged sheets likely to require replacement.

Important: For areas exhibiting damage, the concrete pour must not progress until an appropriate inspection has been carried out and any remedial action implemented.




Go to NEXT section