With composite floor slabs, it is possible to achieve continuous concrete pours in excess of 1,000m2.
  
 +
Where construction joints are required, these should always be formed as close as possible to the deck support at the butt joint in the deck sheets.  The distance from the centre of the end support to the stop end should never exceed one-third of the span between the supports (Refer to Fig 12.5a).
  
  
With composite floor slabs, it is possible to achieve continuous concrete pours in excess of 1,000m2.
+
[[File:12.5a.jpg|400px|link=]]
 
+
Where construction joints are required, these should always be formed as close as possible to the deck support at the butt joint in the deck sheets.  The distance from the centre of the end support to the stop end should never exceed one-third of the span between the supports (Refer to Fig 12.5a).
+
  
 +
'''[https://smdltd.co.uk/wp-content/uploads/2017/01/SMD.DOD_.178.V2-Construction-Joint.pdf Refer SMD Data Sheet SMD.DOD.178 - Construction Joint]'''
  
[[File:12.5a.jpg|400px]]
+
'''[http://www.concretebookshop.com/tr75-composite-concrete-slabs-using-steel-decking-4324-p.asp?dm_t=0,0,0,0,0 Refer Concrete Society TR75 Section 7.5 & SCI P300]'''
  
  
Line 17: Line 17:
  
  
Other items within 12.0 - Concrete:-
+
Go to '''[[12.6 - Reinforcement drawings and bending schedules|NEXT]]''' section
: [[12.1 - Site considerations]]
+
: [[12.2 - Temporary propping]]
+
: [[12.3 - Cleaning the decking]]
+
: [[12.4 - Damaged decking]]
+
: [[12.5 - Construction joints]]
+
: [[12.6 - Reinforcement drawings and bending schedules]]
+
: [[12.7 - Concrete mix requirements]]
+
: [[12.8 - Placement]]
+
: [[12.9 - Surface finish]]
+
: [[12.10 - Surface flatness]]
+
: [[12.11 - Curing]]
+
: [[12.12 - Post-installation characteristics]]
+

Latest revision as of 12:01, 10 May 2018

With composite floor slabs, it is possible to achieve continuous concrete pours in excess of 1,000m2.

Where construction joints are required, these should always be formed as close as possible to the deck support at the butt joint in the deck sheets. The distance from the centre of the end support to the stop end should never exceed one-third of the span between the supports (Refer to Fig 12.5a).


12.5a.jpg

Refer SMD Data Sheet SMD.DOD.178 - Construction Joint

Refer Concrete Society TR75 Section 7.5 & SCI P300


Construction joints should be formed using either timber or one of the proprietary joint systems available for use on composite floor deck profiles. Where a day joint is required, adequate continuity reinforcement must be provided either by extending a sheet of mesh or additional bars through the joint location to provide slab continuity between pours.