9.1 - Delivery and access
Decking and edge trim are delivered on 25 tonne capacity articulated vehicles with trailers up to 13.50m long. On supply and fix contracts, SMD's Contract Team will contact the client to arrange deliveries to suit minimum product lead times required for delivery of materials. Where site access restrictions apply, deliveries can be arranged on alternative vehicles (i.e. 10 tonne rigid or Hi-Ab); contact SMD's Contract Team for further advice.
Upon arrival at site, the driver will allow a maximum two hour off-loading period, unless agreed otherwise with the SMD Operations Team. Typically, the off-loading is undertaken by the steelwork contractor in conjunction with the erection of the steel frame. SMD do not undertake off-loading of delivery vehicles.