9.1 - Delivery and access

From TGN Online
Revision as of 14:24, 25 January 2017 by Admin (Talk | contribs)

Jump to: navigation, search

Back to main Contents page


Decking and edge trim are delivered on 25 tonne capacity articulated vehicles with trailers up to 13.50m long. On supply and fix contracts, SMD Construction Manager will contact the client to arrange deliveries to suit minimum product lead times required for delivery of materials. The seven working days stated does not include the day of call off or the day of delivery, this is purely the manufacturing duration. Where site access restrictions apply, deliveries can be arranged on alternative vehicles (i.e. 10 tonne rigid or Hi-Ab); contact SMD Operations Team for further advice.


9.1a.jpg


Upon arrival at site, the driver will allow a maximum two hour offloading period, unless agreed otherwise with the SMD Operations Team. Typically, the offloading is undertaken by the steelwork contractor in conjunction with the erection of the steel frame. SMD do not undertake offloading of delivery vehicles.




Other items within 9.0 - Supply of materials:-

9.1 - Delivery and access
9.2 - Pack size and sheet length limits
9.3 - Offloading, hoisting and storage
9.4 - Pack labels / loading-out locations