The concrete mix design must be suitable for the intended method of installation (e.g.  pumpable) and finishing.  Concrete with a minimum consistence class of S3 should be utilised, in accordance with BS 8500.
 +
 +
The mix design should be prepared in accordance with the strength class, maximum water/cement ratio and minimum cement content specified the engineer.  The concrete contractors proposed mix design must be approved by the engineer prior to commencement of concrete placement works.
  
 +
 +
'''BS 8500-1:2006 + A1:2012: Concrete. Complementary British Standard to BS EN 206-1. Method of specifying and guidance for the specifier.'''
  
 +
'''[http://www.concretebookshop.com/tr75-composite-concrete-slabs-using-steel-decking-4324-p.asp Refer to 'Concrete Society Technical Report No.75 - Composite slabs using steel decking' for more information]'''
  
Body - First line  
+
'''[https://smdltd.co.uk/wp-content/uploads/2023/10/SCI-P-300-Composite-SLabs-and-Beams-using-steel-decking-Third-Edition.pdf MCRMA/SCI Technical Paper No.  13/SCI P300 REVISED EDITION.  Composite slabs and beams using steel decking: Best practice for design and construction]'''
 
+
Body - Last line
+
  
  
Line 11: Line 14:
  
  
Other items within 12.0 - Concrete:-
+
Go to '''[[12.8 - Placement|NEXT]]''' section
: [[12.1 - Site considerations]]
+
: [[12.2 - Temporary propping]]
+
: [[12.3 - Cleaning the decking]]
+
: [[12.4 - Damaged decking]]
+
: [[12.5 - Construction joints]]
+
: [[12.6 - Reinforcement drawings and bending schedules]]
+
: [[12.7 - Concrete mix requirements]]
+
: [[12.8 - Placement]]
+
: [[12.9 - Surface finish]]
+
: [[12.10 - Surface flatness]]
+
: [[12.11 - Curing]]
+
: [[12.12 - Post-installation characteristics]]
+

Latest revision as of 08:57, 19 October 2023

The concrete mix design must be suitable for the intended method of installation (e.g. pumpable) and finishing. Concrete with a minimum consistence class of S3 should be utilised, in accordance with BS 8500.

The mix design should be prepared in accordance with the strength class, maximum water/cement ratio and minimum cement content specified the engineer. The concrete contractors proposed mix design must be approved by the engineer prior to commencement of concrete placement works.


BS 8500-1:2006 + A1:2012: Concrete. Complementary British Standard to BS EN 206-1. Method of specifying and guidance for the specifier.

Refer to 'Concrete Society Technical Report No.75 - Composite slabs using steel decking' for more information

MCRMA/SCI Technical Paper No. 13/SCI P300 REVISED EDITION. Composite slabs and beams using steel decking: Best practice for design and construction