− | + | The concrete mix design must be suitable for the intended method of installation (e.g. pumpable) and finishing. Concrete with a minimum consistence class of S3 should be utilised, in accordance with BS 8500. | |
+ | |||
+ | The mix design should be prepared in accordance with the strength class, maximum water/cement ratio and minimum cement content specified the engineer. The concrete contractors proposed mix design must be approved by the engineer prior to commencement of concrete placement works. | ||
− | + | ||
+ | '''BS 8500-1:2006 + A1:2012: Concrete. Complementary British Standard to BS EN 206-1. Method of specifying and guidance for the specifier.''' | ||
+ | |||
+ | '''[http://www.concretebookshop.com/tr75-composite-concrete-slabs-using-steel-decking-4324-p.asp Refer to 'Concrete Society Technical Report No.75 - Composite slabs using steel decking' for more information]''' | ||
+ | |||
+ | '''[https://smdltd.co.uk/wp-content/uploads/2016/07/SCI-Publication-P300-MCRMA-TP-No.-013-Best-Practice-Guide-REVISED-EDITION.pdf MCRMA/SCI Technical Paper No. 13/SCI P300 REVISED EDITION. Composite slabs and beams using steel decking: Best practice for design and construction]''' | ||
Revision as of 15:00, 25 January 2017
Back to main Contents page
The concrete mix design must be suitable for the intended method of installation (e.g. pumpable) and finishing. Concrete with a minimum consistence class of S3 should be utilised, in accordance with BS 8500.
The mix design should be prepared in accordance with the strength class, maximum water/cement ratio and minimum cement content specified the engineer. The concrete contractors proposed mix design must be approved by the engineer prior to commencement of concrete placement works.
BS 8500-1:2006 + A1:2012: Concrete. Complementary British Standard to BS EN 206-1. Method of specifying and guidance for the specifier.
Other items within 12.0 - Concrete:-
- 12.1 - Site considerations
- 12.2 - Temporary propping
- 12.3 - Cleaning the decking
- 12.4 - Damaged decking
- 12.5 - Construction joints
- 12.6 - Reinforcement drawings and bending schedules
- 12.7 - Concrete mix requirements
- 12.8 - Placement
- 12.9 - Surface finish
- 12.10 - Surface flatness
- 12.11 - Curing
- 12.12 - Post-installation characteristics